Cypress Lake Estates Building Rehab

Over the next two years, we will be restoring buildings within the Cypress Lake Estates community. Bookmark this page for easy reference.

Did you receive a letter from us?

If you recently received a letter from us letting you know that we will be starting work on your building soon and you would like to submit your information for the additional work to be done (gutter, new screen enclosure and/or closet door), please click the button below.

Schedule

Below are the estimated start and completion dates per building. All unit owners will be notified prior to work starting on the building.

Building # Est. Start Date Est. Finish Date
13 March 29, 2017 May 12, 2017
19 May 15, 2017 June 30, 2017
14 July 3, 2017 August 18, 2017
15 August 21, 2017 October 6, 2017
5 October 8, 2017 November 24, 2017
4 November 27, 2017 January 5, 2018
3 January 8, 2018 February 23, 2018
2 February 26, 2018 April 13, 2018
1 April 16, 2018 June 1, 2018
8 June 4, 2018 July 20, 2018
9 July 22, 2018 September 7, 2018
10 September 9, 2018 October 26, 2018
Carports November 5, 2018 November 16, 2018